Long-Range Plans

 

 

 

Find Information about city and county roads

 


Studies, Plans and Future Projects

 

Find out about studies and plans for possible future projects. Some projects on this list are already scheduled and work will begin in the near future. Get involved in public hearings and the planning process. Learn about the planning process before a highway is built.

 

There is also a list of current construction projects on highways.

 

Select a highway from the list below:

 

 

Hwys 1-36

Hwy 3—Inver Grove Heights
Resurfacing, repairs and drainage improvement on Hwy 3 between Rosenberger Lake (near Anne Marie Trail) and 50th Street East (north of Hwy 110)
Work begins: 2013
Contact: J.P. Gillach

 

Hwy 5—Carver County from Hwy 41 to Hwy 212

Study by Carver County, the cities of Victoria and Waconia and MnDOT to identify possible future improvements. See 2012 Hwy 5 project

Read complete study

Contact: J.P. Gillach

Hwy 7/Louisiana Avenue
Interchange construction
Work begins: 2012
Maps and additional documents
Contact: April Crockett


Hwy 8—Lindstrom

Interregional corridor study

Work begins: 2011

Maps and additional documents

Contact: Todd Clarkowski

 

 

Hwy 10 Elk River

Upgrade to a freeway system: Study

Status:Findings of Fact and Conclusions (PDF) published in March 2012

Study funded by the city of Elk River

Contact: Jim Hallgren, project manager james.hallgren@state.mn.us

 

Hwy 10—Ramsey

Preliminary Interchange Design
Work begins: N/A

Maps and additional documents

Contact: Mark Lindeberg, 651-234-7722

 

Hwy 10—Anoka

Work begins: N/A

Maps and additional documents

Contact:Carolyn Braun

 

Hwy 13—Burnsville Interchange (at Hwy 5)

New interchange and frontage roads

Work begins:N/A

Maps and additional documents

 

Hwy 13 between I-35E in Lilydale and Second Street in Mendota
Description: Resurfacing, signal, drainage, pedestrian and trail improvements
Construction Dates: Summers of 2011, 2012 and 2015
Contact: J.P. Gillach


Hwy 14—from Nicollet County Hwy 6 to Lookout Drive in North Mankato

Reconstruction and improvements

Work begins: 2011

Maps and additional documents

Contact: Matthew Rottermond

 

Hwy 14—New Ulm to N. Mankato

Environmental Impact Statement

Work Begins: 2015

Environmental impact studies, alternatives, public involvement

Contact: Peter Harff

 

Hwy 14—between Owatonna and Dodge Center

South bypass alignment

Work begins: Once funding is available

Maps and additional documents

Contact: Heather Lukes

 

Hwy 15 — Sartell/St. Cloud

Construct a diverging diamond interchange at Stearns County Road 120

Work begins: July 2012 - November 2013; 2012 - prep work, 2013 - construct interchange

Maps and additional documents for project

Contact: Claudia Dumont, project development manager or Tim Paul, construction supervisor

 

Hwy 23—Paynesville area

Improvements

Work begins: N/A

Maps and Additional Documents

Contact: Lowell Flaten

Hwy 23/71—Kandiyohi County

Improvements

Work begins: 2015

Maps and additional documents

Contact: Lowell Flaten

 


 

I-35 in Burnsville/Lakeville
Construct two noisewalls at I-35/County Road 46 interchange. One noisewall in northeast quadrant along Kenrick Avenue, and one noisewall in northwest quadrant along Buck Hill Road. See proposed noisewall locations.
Work begins: 2015
Contact: J.P. Gillach

 

 

I-35W from Minneapolis to Forest Lake
Managed lane study
Contact: William Goff

 

I-35W and Hwy 13 Burnsville Interchange

New interchange and frontage roads

Work begins: N/A

Maps and additional documents

Contact:J.P. Gillach

 

I-35W Bus Rapid Transit Study

Study

Videos and Final Report

 

I-35W—Transit/Access Project
Transit improvements near Lake Street
Work Begins: N/A

To view the Request For Qualifications, go to the Hennepin County Web site

 

Hwy 36—St. Croix Crossing Project

New bridge and trails connecting Minnesota and Wisconsin

Work begins: 2014

Project information

Contact: Mary McFarland

 

Hwy 36—Stillwater Lift Bridge
Repair bridge

Maps and additional documents

Contact: Kevin Walker

 

Hwy 36 at English Street in Maplewood
Construct new diamond interchange between Hwy 36 and English Street

Work begins: 2014
Contact:  Kent Barnard

 

Hwy 36—Hilton Trail in Pine Springs
Intersection Reconstruction 2013

Additional information

Contact: Curt.Fakler@state.mn.us

 

Hwys 41-100

 

Hwy 41—River Crossing Project

Study Details

Contact: Diane Langenbach

 

Hwy 41—Minnesota River Flood Study

Flood Mitigation on Hwys 41, 101 and 169

Contact: JP Gillach

 

Hwy 43—Winona Bridge

Bridge replacement

Work begins: 2014

Maps and additional documents

 

Hwy 51, Snelling Avenue

Multi-modal study

Maps and additional information

Contact: William Goff

 

Hwy 52—City of Cannon Falls

New interchange

Work begins: N/A

Maps and additional information

Contacts: Kristine Kammueller

 

Hwy 52 in Inver Grove Heights
Proposed frontage road near Concord Boulevard/County Hwy 56. Tentatively scheduled to begin summer 2012.
Maps and additional information
Contact: J.P. Gillach

 

Hwy 52 and Hwy 12 in Pine Island—Elk Run Development

New interchange

Additional Information

Contact:Kristine Kammueller
Five design-build teams selected to vie for Hwy 52 interchange project


Hwy 52 in North Rochester

Northern Rochester Transportation Study (City of Rochester)

Contacts: Jeff Bunch

 

 

Hwy 52 in Hampton

Intersection Improvements

Contacts: Diane Langenbach

 

Hwy 52 at CR 86—Randolph Township (just north of Cannon Falls)
Replace existing intersection with Reduced Conflict Intersection
Work begins: 2013
Maps and additional information
Contacts: J.P. Gillach

 

Hwy 52 and Dakota County 42 in Rosemount
Interchange reconstruction. Joint project between MnDOT and Dakota County
Status: Proposed
Additional Information
MnDOT Contact:J.P. Gillach

 

Hwy 52 Cannon Falls to Hader Access Study

Status: Study

Additional Information

Contact: Healther Lukes

 

Hwy 53—Between Eveleth and Virginia

Relocation of the highway

Status: Environmental work is now needed to select a preferred alignment alternative. Public input will be solicited during future scoping meetings to assist in identifying alternatives.

Maps and additional documents

Contact: Roberta Dwyer

 

Hwy 53, Virginia to Cook

Four-lane expansion project
Work begins: Winter 2012

Maps and additional information

Contact: Brian Larson

 

Hwy 55—Annandale to Rockford

Four lane expansion

Work begins: Currently unscheduled

Maps and additional information

Contacts: Claudia Dumont

 

Hwy 55—Plymouth to Rockford

Lane expansion

Work begins: N/A

Maps and additional information

Contact: James Grube

 

Hwy 59—Pelican Rapids

Resurfacing, bridge replacements

Work begins 2012

Additional information

Hwy 60 in Worthington

Description: Part of the Hwy 60 expansion project

 

Hwy 60 - Worthington Travel Information Center
Closed because of the reconstruction of Hwy 60
Closed until November 2011
Worthington Travel Information Center closed

Contact: List of e-mails and people to contact about Rest Areas

 

Hwy 60 Windom to St. James
Description: Four- lane reconstruction
Contact: Steve Bowers


 

Hwy 63 Bridges—Red Wing

Rehabilitate existing bridges, identify a preferred alternative for a bridge crossing between Red Wing, Minn. and Wisconsin, view Hwy 63 Bridges project website for more info.

Contact: Kristin Kammueller

Hwy 71/23—Kandiyohi County

Work begins: 2015

Maps and additional documents

Contact: Lowell Flaten

 

Hwy 77—Cedar Avenue in Apple Valley and Bloomington

Study to find ways to relieve congestion

More Information

Contact: Brian Kary

 

I-90—Bridge near Dresbach

Study

Work begins: 2012

More information

Contact: Kristin Kammueller


I-94 to Hwy 10 Interregional Connection Clearwater to Clear Lake

River crossing and freeway connection

Work begins: Unscheduled

Maps and additional documents

Contact: Terry Humbert

 

I-94 East Metro Corridor Study

Traffic forecasts and operations study

Contact: Bill Goff

 

I-94 Chatsworth Pedestrian Bridge

Build pedestrian bridge

Work begins: Summer 2012

Contact: Kent Barnard

 

I-94, Hwy 15, Hwy 52 Greater Minnesota interchange projects

Improved interchange project

Work begins: Summer 2012

Additional Information

Contact: Terry Humbert

 

 

Hwy 95 Taylors Falls
Pavement rehab and culvert replacement
Work begins: 2013
Additional Information
Contact: Kevin Walker

 

Hwy 100 St. Louis Park
Interchange reconstruction
Work begins: 2015
Additional Information
Contact: April Crockett

 

Hwys 101-694

 

Hwy 101 Chanhassen

Study

Additional information

Construction 2013-City of Chanhassen

Environmental study

Contact: Paul Oehme

Hwy 101/County Hwy 144 in Rogers
Proposed interchange construction
Work Begins: 2014
Contact: Ramankutty Kannankutty

 

 

Hwy 101 —Minnesota River Crossing

Flood Mitigation Project

Contact: JP Gillach

 

Hwy 169—Belle Plaine Area

Study (PDF, about 40 pages)

 

Hwy 169 and Hwy 41—River Crossing Project

Study and Environmental Impact Statement

Contact: Diane Langenbach

 

Hwy 169 in Blue Earth

Reconstruct and resurface

Work begins: 2012

 

Hwy 169 at Scott County Hwy 69 in Shakopee
Description: Construct interchange to replace at-grade intersection. Project is led by Scott County.

 

Hwy 169/County Hwy 30 (93rd Ave N)
Proposed interchange construction
Work Begins: 2013

Contact: Bre Grand

 

Hwy 169 —Minnesota River Flood Study

Flood Mitigation on Hwys 41, 101 and 169

Contact: JP Gillach

 

Hwy 169 Bloomington Ferry Bridge – at Minnesota River near Savage, Bloomington, Shakopee
Bridge repair
Work Begins: 2013
Contact: JP Gillach

 

Hwy 169—Elk River to Zimmerman

Add interchanges and frontage roads: Study

Status: Environmental Assessment, Environmental Assessment Worksheet and Draft Section 4(f) Evaluation is open for public review and comments thru Dec. 20, 2010. Study funded by the city of Elk River. Study funded by the city of Elk River.
Contact: Jim Hallgren, project manager james.hallgren@state.mn.us

 

 

Hwy 212—Norwood Young America

Lane expansion

Work begins: N/A

Maps and additional documents

Contact: Nicole Peterson

 

Hwy 212—Cologne

Transportation planning study

More information

 

Hwy 212 connection to Hwy 169 and Hwy 41 River Crossing Project

Study and Environmental Impact Statement

Contact: Diane Langenbach

 

Hwy 294—Willmar

Study

More information

Contact: Diane Beck

 

Hwy 316 through Hastings

Study

More information

Contact: Ken E. Johnson

 

Hwy 371—Nisswa to Pine River

Expansion to four lanes

Work begins: 2018

Maps and additional documents

Contact: Jim Hallgren

 

I-494 Between I-394 and East Fish Lake Road

 

 

I-694 Interchange and White Bear Ave.

Reconstruction project

Work begins: N/A

More information (City of Maplewood)

 

 

Hwy 952A /South Robert Street — West St. Paul between Mendota Road and Annapolis Street
Roadway and pedestrian safety improvements
Work begins: 2013
Maps and additional information
Contact: Matt Saam, city of West St. Paul